Client:
South African Airways

Project:
Terminal 2 office fit out

Project Detail :

Project AQ picked up the concept designs early in October 2014 and used their understanding of the Heathrow standards and terminal 2 permit process to create the office space within 10 days off approvals.  Project consisted of ceilings, partitions, floor finishes and kitchen space with a detailed coloured glass splash backThe project was under tight timelines due to South Africans late engagement and requirement to relocate from Terminal 1 however due to a pragmatic programme and pro activeness approach from Heathrow South African Airlines took ownership and moved in per programme